1. The first step is to get an estimate. An estimate includes a site visit or home visit to measure the square footage of the work area. Within 24 hours of the visit, you will receive an estimate and tile quantities required for your project.
2. Once the square footage and the estimate are determined, you can begin to shop for tile. We are happy to recommend local tile shops.
3. Once your tile has been picked up or delivered, work can begin on your project. Demo on a standard shower takes one day to complete. Prep work, such as waterproofing for a shower, takes about two days. (Not all jobs require waterproofing and will move faster.)
4. Installation for a standard shower takes approximately 7-10 working days from start to finish. The time frame to complete your project is dependent on the size of the tile, material the tile is made of, and layout of the tile.
Installation for a backsplash or small laundry room floor will take 2-3 working days from start to finish.
5. After installation, a final clean will be done and you can begin to enjoy your new tile.